Hilton Hotel — @40 Complex Building
New Cairo, Egypt
- Built-up area
- 28,000 m²
- Connected load
- ≈ 4 MVA
Technical assistance on site from mobilisation to handover, ending with testing and commissioning of all MEP works.
Evolution follows up the activities of the contractors on site, reviews and approves the documents the works depend on, and carries out testing and commissioning of all MEP works before handover.
Site supervision has been provided on projects including the Hilton hotel at the @40 complex, Palm Royale Resort in Soma Bay, Memphis University, the GIU and GUC campuses, the University of Hertfordshire building in the New Capital and the Kozzika workshop of Cairo Metro Line 1.
New Cairo, Egypt
Soma Bay, Egypt
New Administrative Capital, Egypt
New Administrative Capital, Egypt
New Administrative Capital, Egypt
Following up the activities of the contractors, reviewing and approving material submittals, material inspection requests and site inspection requests, reviewing payment invoices, and carrying out testing and commissioning of all MEP works.
Concept, preliminary and detailed design of electromechanical installations for buildings.
Outdoor utility networks, feeding points and road lighting for cities, resorts and compounds.
Complete tender packages: design drawings, technical specifications, bills of quantities and cost estimates.
Checking bids for sufficiency and conformity, and ranking contractors by their technical offers.